US AI data center power gap

The gist

RAND Finds Only 33 GW Net New US Grid Power Available for AI by 2030

Multiple forecasters now project US data center power demand near or above 100 GW by 2030, while RAND's analysis of the interconnection queue suggests only about 33 GW of net new grid capacity will realistically be available for that purpose. The gap is driving infrastructure workarounds including SpaceX's move to manufacture turbine parts in-house.

The full picture

A RAND analysis of the US electricity interconnection queue found that of 1,086 GW of planned generation capacity, roughly 33 GW of net new power will realistically be available to serve AI data centers by 2030, after accounting for project withdrawals, reliability constraints, and planned retirements. Against that constrained supply, demand forecasts have risen sharply: BloombergNEF revised its 2030 US data center capacity projection upward by 52% to 118 GW, and 83% upward to 194 GW by 2035. 451 Research projects US data center grid power demand will reach 61.8 GW in 2025 and 134.4 GW by 2030. TrendForce projects global data center capacity will grow from 100.5 GW in 2024 to 211.1 GW by 2027, with AI servers accounting for roughly one quarter of global data center power demand in 2025 and potentially exceeding 40% by 2027. The Electric Power Research Institute estimates data centers could consume 9% to 17% of all US electricity by 2030.

On the supply side, SpaceX has begun bringing turbine blade and vane casting in-house to address bottlenecks caused by US grid connection delays pushing AI data center projects toward portable natural gas turbine generators. Elon Musk said the move could cut generator procurement delays by 18 months. Turbine blade production currently takes 60 to 90 weeks per batch. Howmet Aerospace, which holds roughly half of the global market share for natural gas turbine components, saw its stock fall more than 7% following the announcement before partially recovering.

How it developed
25 September 2026

RAND found on September 25 that only about 33 GW of net new US grid capacity will realistically be available for AI data centers by 2030 from a nominal 1,086 GW pipeline, after accounting for project withdrawals, reliability constraints, and retirements.

Against that ceiling, BloombergNEF raised its 2030 US data center demand forecast 52% to 118 GW and 451 Research projected 134.4 GW by 2030. SpaceX announced it has begun casting turbine blades and vanes in-house, which Elon Musk said could cut generator procurement delays by 18 months, sending Howmet Aerospace stock down more than 7%.

19 September 2026

Overview of US power infrastructure gap: TrendForce and EPRI projections cited; US supply-demand gap could exceed 170 GW by 2030

11 September 2026

Financial Times reports SpaceX's turbine parts plan; notes competitive threat may ease supply bottleneck even absent full-scale manufacturing

2 September 2026

SpaceX confirms foundry plans to cast natural gas turbine blades and vanes for AI data centers

30 August 2026

SpaceX begins in-house turbine blade manufacturing; move expected to cut generator procurement delays by 18 months; Howmet Aerospace stock drops more than 7%

29 July 2026

BloombergNEF releases revised US data center forecast: 118 GW by 2030 (up 52% from Dec 2025 estimate) and 194 GW by 2035 (up 83%)

29 April 2026

RAND publishes analysis finding only 33 GW net new US grid capacity realistically available for AI data centers by 2030 from 1,086 GW interconnection queue