The Information Machine
Following·Day 356·first covered 6 Oct 2025·8 sources

BNEF Raises US Data Center Power Forecast 52%; Grid Supply Gap Persists

The gist

The gap between forecast demand and the realistic supply available from the grid by 2030 is substantial, with RAND's analysis putting net available new capacity at roughly 33 GW against forecasts ranging from 118 to 134 GW. Hyperscalers are responding by locking in long-term nuclear agreements, including deals involving plants that would otherwise have closed.

The full picture

BloombergNEF now forecasts 118 GW of installed US data center capacity by 2030 and 194 GW by 2035, representing upward revisions of 52% and 83% respectively from its December 2025 forecast. 451 Research, cited by S&P Global, projects US data center grid power demand will reach 61.8 GW in 2025 and 134.4 GW by 2030, roughly triple 2025 levels. On the supply side, a RAND analysis found that the US interconnection queue holds approximately 1,086 GW of planned generation, but after removing projects without reliable deliverability status, applying historical withdrawal rates, accounting for capacity accreditation factors, transmission and distribution losses, and planned retirements, net available capacity for data center power needs falls to approximately 33 GW. Against this backdrop, major hyperscalers have pursued nuclear power agreements as a direct power sourcing strategy.

How it developed
25 September 2026

Alphabet reported to be funding nuclear capacity increases at two Georgia plants supplying its data centers

18 September 2026

Data Center Dynamics documented hyperscaler nuclear agreements including AWS-Talen, Google-Kairos, and Equinix-Oklo deals

29 July 2026

BloombergNEF raised US data center capacity forecast to 118 GW by 2030 and 194 GW by 2035, revisions of 52% and 83% from December 2025

2 June 2026

Carnegie Endowment detailed Alphabet-Kairos-TVA molten-salt reactor deal, Meta-Constellation Clinton plant credit purchase, and Meta-Oklo 1.2 GW Ohio campus agreement

29 April 2026

RAND published analysis finding net available grid capacity for data centers by 2030 is approximately 33 GW from a 1,086 GW interconnection queue

6 October 2025

Meta and Microsoft each signed 20-year PPAs with Constellation Energy for nuclear power

Sources
3 more sources
The daily email

Want this in your inbox?

I send one email each morning with the stories that moved. If you would rather just read here, that works too.

Subscribe free