US data center siting opposition

The gist

Latest: Goldman Sachs: 45% of US Data Center Capacity Faces Moratorium Risk

A substantial share of planned US AI data center capacity faces potential delays from regulatory and community opposition. The Ohio ballot initiative, if it qualifies, could set a precedent for similar efforts in the 23 states that allow citizen-initiated ballot measures.

When stories like this move, I write about them in an email each morning.

One free email each morning, around 8 AM US Eastern.

The full picture

Following Democratic victories in the House, Senate, and key governorships, Goldman Sachs warned that short-term moratoria could affect about 45% of planned US data center capacity, with states like Texas and Ohio potentially halting construction pending community assurances on water and electricity. Meta President Dina Powell McCormick said the elections will make data center construction "going to be harder" and that every hyperscaler is now considering building outside the US. McCormick also acknowledged the AI industry undersold the benefits of data centers to the public.

The regulatory pressure predates the election results. A Goldman Sachs podcast from September 2026 found that over 300 regional or local restrictions had already emerged, with public opposition and regulatory uncertainty identified as the primary obstacles to data center expansion. In Ohio, which hosts nearly 200 data centers, advocates are pursuing a 2026 ballot measure that would ban data centers requiring 25 MW or more of power, covering most AI-focused facilities. Advocates must gather 413,488 valid signatures by July 1 to place the measure on the November 2026 ballot. The Ohio effort follows Maine Governor Janet Mills' veto of a state data center moratorium, with advocates turning to ballot measures as an alternative path.

How it developed
6 November 2026

McCormick acknowledges the AI industry undersold the benefits of data centers to the public

5 November 2026added 14 Nov

Goldman Sachs warned after Democratic election victories that moratoria could affect about 45% of planned US data center capacity; Meta President Dina Powell McCormick said every hyperscaler is now considering building outside the US.

A September 2026 Goldman Sachs podcast had already counted over 300 regional and local restrictions and named public opposition as the primary obstacle. In Ohio, advocates pursuing a ballot measure to ban data centers requiring 25 MW or more must gather 413,488 signatures by July 1, 2026.

1 September 2026

Goldman Sachs podcast counts over 300 regional/local restrictions and identifies public opposition as the primary industry obstacle

7 May 2026

Ohio advocates pursue ballot measure to ban data centers requiring 25 MW or more; signature deadline set for July 1